Updated: March 15, 2023
NGCP requested scheduled power interruption on MARCH 18, 2023 (SATURDAY) for their scheduled maintenance work. Thus, MORE Power will conduct parallel line works simultaneous to NGCP.
NGCP’s SCHEDULED POWER INTERRUPTION:
DATE: 18 March 2023 (Saturday)
TIME: 6:00 AM – 5:00 PM (11 hours)
AFFECTED FEDERS:
> PORTION OF FEEDERS 2 & 3
SMDC
Portion of Cubay
Portion of Balabago
Portion of Hinactacan
Portion of Banuyao
MORE POWER’S SCHEDULED POWER INTERRUPTION:
Date: 19 MARCH 2023 (SUNDAY)
Time: 6:00 AM to 1:00 PM (7 hours)
Affected Feeder:
>PORTION OF JARO FEEDER 2
REMONVILLE SUBDIVISION TABUC SUBA, JARO
MODERN HOMES SUBDIVISION TABUC SUBA, JARO
Scope of Works
- Replacement of dilapidated primary poles with 40ft concrete poles.
- Replacement of wooden cross arm with steel.
- Re-tensioning of Primary lines.
- Transfer of Distribution transformer from old pole to new concrete pole.


Greetings from Iԁaho! I’m bored to deɑth at work so I decided to check out your site on my iphone during lunch break. I enjoy the info ʏou provide here and can’t wait to take a looк when I get home.
Thank you Main! Iloilo City will see you soon.
Will the power come back on time?
Yes.